Project | 5th Ave Pipeline Replacement Project - Fire Flow Improvement Program |
Program | A2A Fire Flow Improvement Program |
Project Number | F18003 |
Contact | Zak Talbott | ZTalbott@marinwater.org |
Project Description
Installation of 2,700 feet of 18-inch welded steel pipe to replace vulnerable and dated 14” cast iron pipe in San Rafael from 1927. This project is to improve fire flow and seismic reliability in this area.
Benefits
The Fire Flow Improvement Program 5th Ave Pipeline Replacement Project will install new pipe to replace old, undersized fire flow deficient pipe in the City of San Rafael in coordination with other municipal projects in the area to minimize impact to the public.
Schedule and Status
Planning: Fall 2017 - Fall 2020
Design: Fall 2020 - Spring 2021
Construction: Spring 2021 - Fall 2021 | Completed
Expenditure Schedule
Actuals ThroughFY 22 |
Total |
$2,762,766 |
$2,762,766 |
Funding Sources
Capital Maintenance Fund |
Fire Flow Improvement Program Fund |
Total |
- |
$2,762,766 |
$2,762,766 |