Project Description 

Installation of 2,700 feet of 18-inch welded steel pipe to replace vulnerable and dated 14” cast iron pipe in San Rafael from 1927. This project is to improve fire flow and seismic reliability in this area. 

Benefits

The Fire Flow Improvement Program 5th Ave Pipeline Replacement Project will install new pipe to replace old, undersized fire flow deficient pipe in the City of San Rafael in coordination with other municipal projects in the area to minimize impact to the public. 

Schedule and Status

Planning: Fall 2017 - Fall 2020

Design: Fall 2020 - Spring 2021

Construction: Spring 2021 - Fall 2021 | Completed

Expenditure Schedule

Actuals Through
FY 22
Total
$2,762,766
$2,762,766

Funding Sources 

Capital Maintenance Fund 
Fire Flow Improvement Program Fund
Total
-
$2,762,766