Project | Berry Lane Pipeline Replacement Project |
Program | A1A02A Replacements - Distribution Pipelines |
Project Number | D21007 |
Contact | Matthew Steiner | MSteiner@marinwater.org |
Project Description
Installation of approximately 300 feet of 4-inch piping from the intersection of Berry Lane and Sir Francis Drake Blvd. to #8 Berry Lane. This project replaced an existing 4-inch cement lined cast iron pipe originally installed in 1938.
Benefits
Prior to this project, the original line had reached the end of its useful life and was beyond repair, resulting in an above ground plastic pipeline to temporarily serve the customers on Berry Lane. Performing this project allowed for the new pipeline to be installed underground increasing the safety and reliability of service to these customers.
Schedule and Status
Planning: Summer 2020 - Spring 2021
Design: Spring 2021 - Summer 2021
Construction: Summer 2021 - Winter 2021/22 | Completed
Expenditure Schedule
Actuals ThroughFY 22 |
Total |
$317,733 |
$317,733 |
Funding Sources
Capital Maintenance Fund |
Other Funding Sources |
Total |
$317,733 |
- |
$317,733 |