Construction Update
Work has commenced on Courtright system improvements that will enable the District to permanently decommission and eventually remove the 49-year-old Courtright Tank in the Bret Harte Road area. The work is scheduled to take a couple of months, and involves the installation of 520 feet of 8-inch pipeline, as well as a new pressure regulator valve.
The Courtright Systems Improvement Program is the latest example of the District’s work to replace, decommission or upgrade redwood water tanks. This tank is one of just six leak-prone redwood tanks remaining, out of a total of 130 tanks throughout the District’s service area.
Project Schedule & Road Safety During Construction
- Construction will take place 8 a.m. to 5 p.m. weekdays. Note: Setup and cleanup activities may occur outside of this timeframe.
- Marin Water and its contractor, D&D Pipelines, 415-482-6510, will take all measures possible to minimize inconveniences associated with the project, including efforts to limit noise and traffic delays.
- Please be aware of heavy equipment and construction personnel on the roadway, reduce your speed and follow relevant traffic control signs at all times.
Potential Water Service Impacts
Water service may be interrupted for short periods during construction. Residents will be notified prior to service interruptions. If the interruption will last a full day, Marin Water will provide 24-48 hours notice to customers via a hanging tag on a gate or doorway. If a medical condition exists which requires that you receive continuous water service, please notify us at the number below as soon as possible.
Contact Information
- Phone: Marin Water Construction Management team, 415-945-1560
Maintaining Infrastructure is Top Priority
Marin Water provides safe, reliable, local drinking water to 191,000 customers spanning 10 towns and cities in a 147-square-mile section of central and southern Marin County. Updating the District’s aging infrastructure, including leak-prone redwood water tanks, is critical to ensuring the reliability and resiliency of the district's water service delivery system for many years to come.
Project | Courtright System Improvement |
Program | A1A11 Replacements - Storage Tanks |
Project Number | D22009 |
Contact | Mark Kasraie | MKasraie@marinwater.org |
Project Description
Installation of a pressure regulator station and piping improvements. This project will join the Courtright system with the Bret Harte system with a pressure regulator and remove the seismically deficient redwood tank as part of the redwood tank replacement program.
Benefits
The benefit of this project is to improve seismic resiliency of the Courtright System by removing an old leaking redwood storage tank and installing a pressure regulator to provide safe water pressure to customers.
Schedule and Status
Planning: Spring 2021 - Summer 2021
Design: Summer 2021 - Summer 2022
Construction: Summer 2022 - Fall 2022
Expenditure Schedule
Actuals ThroughFY 22 (Rounded) |
FY 23Estimate |
Total |
$17,000 |
$460,000 |
$477,000 |
Funding Sources
Capital Maintenance Fund |
Other Funding Sources |
Total |
$477,000 |
- |
$477,000 |