Kastania Pump Station & Hydraulics Phase I

Project Kastania Pump Station & Hydraulics Phase I 
Program A1A07 Replacements - Transmission Pumps 
Project Number D21027
Contact Mark Kasraie | MKasraie@marinwater.org 
Image
Map of Redwood Hwy and Kastania Rd
Image
Construction site with workers, piping, and equipment

Project Description 

In connection with the 2021 drought, the District acquired, rehabilitated, and recommissioned the Kastania Pump Station, which enables the District operational flexibility to meet its water supply needs when they cannot be met through gravity flow on the North Marin Aqueduct. Project installed approximately 220 linear feet of 30-inch welded steel piping, valves and other appurtenances, and performed a 30-inch hot-tap of the North Marin Aqueduct. 

Benefits

This project adds a critical booster pump station to Marin Water’s infrastructure portfolio and allows for improvements to drought resiliency. The project increases Marin Water’s supply yield up to 4,300 acre-feet per year. 

Schedule and Status

Planning: Winter 2020/21 - Spring 2021

Design: Spring 2021 - Fall 2021

Construction: Fall 2021 - Spring 2022 | Completed

Expenditure Schedule

Actuals Through 
FY 22 
Total
$2,092,213
$2,092,213

Funding Sources 

Capital Maintenance Fund 
Rate Stabilization
Total
$742,213
$1,350,000
$2,092,213