Ridge Road - Fire Flow Improvement Program

Construction Update

This project, which was completed in August 2022, included nearly a mile of welded steel pipe beneath the Town of Tiburon to boost water volumes at existing fire hydrants and also allow the district to install new hydrants to bolster fire resiliency. 

View Project Map

The work was part of a multi-year effort to upgrade portions of the District’s distribution system to provide greater water flows for use by firefighters in the event of a fire. 

Contact Information

  • Phone: Marin Water Construction Management team, 415-945-1560

Fire Safety and Emergency Preparedness Critical

This project – installing a larger water pipeline – increases the volume of water available for fighting fires as part of Marin’s Fire Flow Program. Developed together with residents, city and county officials, area fire chiefs and residents – and approved by voters - the Marin Fire Flow Program is being implemented by Marin Water over the next 15 years to address a key public safety concern in the region. 

Project Ridge Road - Fire Flow Improvement Program 
Program A2A Fire Flow Improvement Program 
Project Number F21002
Contact Dion Mokhtari | DMokhtari@marinwater.org 
Image
Map of pipe location along Lagoon View Dr, Ridge Rd, Mountain View Dr, and Straits View Dr near Hill Haven Tank
Image
Road with tall trees on the left and grass, a house, and body of water on the right

Project Description 

The project will install approximately 5,100 feet of 8-inch welded steel pipe and 450 feet of 10-inch HDPE pipe to replace old, leak prone cast iron pipe installed in 1953 in support of the District’s Fire Flow Improvement Program. 

Benefits

This project will replace leak prone, fire flow deficient pipe with new seismically resilient pipe and improve fire flow within this community. 

Schedule and Status

Planning: Winter 2020/21 - Spring 2021

Design: Spring 2021 - Winter 2021/22

Construction: Winter 2021/22 - Fall 2022 | Completed

Expenditure Schedule

Actuals Through 
FY 22 (Rounded) 
FY 23 
Estimate 
Total
$2,114,000
$100,000
$2,214,000

Funding Sources 

Capital Maintenance Fund 
Fire Flow Improvement Program Fund
Total
-
$2,214,000
$2,214,000