Project | San Clemente Tank System Improvement |
Program | A1A16 Program Management |
Project Number | D18027 |
Contact | Dion Mokhtari | DMokhtari@marinwater.org |
Project Description
This project requires making the following changes in order to improve water quality at San Clemente Tank and reduce demand on Ross Reservoir during peak times:
- Replace the existing 12” butterfly valve (VA-3746), with a 12” SCADA controlled butterfly valve.
- Close valve VA-4911A.
- Replace valve VA-6352B with a 12” check valve.
Benefits
This project will allow for more turn over in the San Clemente Tank, which will result in better water quality and pressure to the surrounding services.
Schedule and Status
Planning: Winter 2017/18 - Spring 2021
Design: Spring 2021 - Summer 2022
Construction: Summer 2022 - Winter 2022/23
Expenditure Schedule
Actuals ThroughFY 21 |
FY 22Estimate |
FY 23Estimate |
Total |
$48,737 |
$4,368 |
$750,000 |
$803,105 |
Funding Sources
Capital Maintenance Fund |
Other Funding Sources |
Total |
$803,105 |
- |
$803,105 |