Project | Sky Oaks Road Retaining Wall Replacement |
Program | A1E05 Watershed ‐ Road Repair and Improvements |
Project Number | D22027 |
Contact | Mark Kasraie | MKasraie@marinwater.org |
Project Description
Replacement of a failing retaining wall on Sky Oaks Road near culvert SO-11 in preparation for Pine Mountain Tunnel Tanks construction traffic.
Benefits
The benefit of replacing the Sky Oaks Road retaining wall is that it will remove the failing log retaining wall and replace it with a soldier pile wall with reinforced concrete lagging that is seismically resilient and protect the integrity of Sky Oaks Road. This project is to prepare Sky Oaks Road for the truck traffic from the Pine Mountain Tunnel Tanks Replacement Project and for future use of visitors to the watershed.
Schedule and Status
Design: Winter 2021/22 - Summer 2022
Construction: Summer 2022 - Fall 2022 | Complete
Expenditure Schedule
Actuals ThroughFY 22 (Rounded) |
FY 23Estimate |
Total |
$19,000 |
$320,000 |
$339,000 |
Funding Sources
Capital Maintenance Fund |
Other Funding Sources |
Total |
$339,000 |
- |
$339,000 |