Project | Southern Marin Pipeline Replacement Project |
Program | A1A02A Replacements - Distribution Pipelines |
Project Number | D20022 |
Contact | Mark Kasraie | MKasraie@marinwater.org |
Project Description
This project will replace 5,580 feet of leak prone piping installed as early as 1924. The project comprises approximately 4,450 feet of welded steel pipe and approximately 1,130 feet of 10-inch HPDE pipe. This project is in coordination with City of Belvedere’s earthquake resiliency program, Sanitary District No. 5’s 2020 Cove Road Force Main Replacement Project and planned upcoming paving work.
Benefits
The benefit of this project is to replace leak prone piping installed as early as 1924 in coordination with City of Belvedere’s earthquake resiliency program, Sanitary District No. 5’s 2020 Cove Road Force Main Replacement Project and planned upcoming paving work to minimize inconvenience to the public.
Schedule and Status
Design: Summer 2019 - Winter 2020/21
Construction: Winter 2020/21 - Spring 2022 | Completed
Expenditure Schedule
Actuals ThroughFY 22 |
Total |
$3,210,239 |
$3,210,239 |
Funding Sources
Capital Maintenance Fund |
Other Funding Sources |
Total |
$3,210,239 |
- |
$3,210,239 |