Skip to main content

Alpine/Bon Tempe Barge Improvements Project

Project Alpine/Bon Tempe Barge Improvements Project
Program Watershed | A1A05 Reservoir/Dam Facilities
Project Number D24010
Contact Ava Pridgeon | apridgeon@marinwater.org 
Image
A floating barge on a lake in front of a tree-covered shoreline.

Project Description 

This project will install an anchorage and flotation system for 12- and 30-inch high density polyethylene pipelines, as well as an anchoring system for the 200 horsepower pump barges. It will also re-secure electrical and communication lines on the 12- and 24-inch high density polyethylene barge pump lines and connect barge platforms. The work calls for the design and installation of deeper intake suction lines to allow for drawing water at different water depths, replacing overflow sluice gate actuators and providing necessary cathodic protection at Alpine Dam intake tower. 

View Project Map 

Benefits

These improvements will provide and maintain system integrity for the current barge systems that convey water from Alpine Lake to Bon Tempe Reservoir, ensuring a reliable water supply. 

Schedule and Status

Planning: N/A

Design: Summer 2023 - Spring 2024

Construction: Spring 2024 - Summer 2024

Funding Sources 

Capital Maintenance Fund 
Other Funding Sources 
Total
$300,000
$300,000