Kastania Pump Station Phase II

Phase II of the Kastania Pump Station Rehabilitation project includes replacement of one pump and motor, as well as installation of a new pressure relief valve and associated tank. 

View Project Map

Schedule and Status

Project currently in design. Construction on hold pending identification of funding.

Contact Information

  • Marin Water Construction Management team:  415-945-1560

Investing in your water system

This project will replace an existing dilapidated pump and motor to increase reliability and resiliency. The installation of a pressure relieve valve and tank will protect the North Marin Aqueduct against potential surge events.   

Funding Sources 

Capital Maintenance Fund 
Other Funding Sources*
Total
$1,500,000
-
$1,500,000