Skip to main content

San Geronimo Creek Crossing Pipeline Replacement Project

Project San Geronimo Creek Crossing Pipeline Replacement Project 
Program A1A02A Replacements - Distribution Pipelines 
Project Number D21042
Contact Dion Mokhtari | DMokhtari@marinwater.org 
Image
Map of bridge location off of Sir Francis Drake Blvd
Image
A rode and bridge surrounded by trees

Project Description 

Temporary relocation of 160 feet of 6-inch pipe from Mountain View Rd Bridge onto a temporary utility crossing. This project is in coordination with Marin County’s Mountain View Rd Bridge replacement project. 

Benefits

This project will relocate the water main on a new seismically resilient concrete bridge that the Marin County Public Works Department is constructing. This section of water main provides system redundancy for the community in that area and for fire protection.  

Schedule and Status

Planning: Winter 2020/21 - Summer 2021

Design: Summer 2021 - Fall 2023

Construction: Fall 2023 - Winter 2023/24

Expenditure Schedule

Actuals Through 
FY 22 (Rounded) 
FY 23 
Estimate 
Total
$47,000
$220,000
$267,000

Funding Sources 

Capital Maintenance Fund 
Other Funding Sources 
Total
$267,000
$267,000