This project involves the installation of approximately 3,850 feet of 8- and 6-inch welded steel pipe to replace undersized, fire flow-deficient and leak-prone 4-inch cast iron pipe.
Schedule and Status
Design: Fall 2024 - Fall 2025
Construction: Winter 2026 - Summer 2026
Contact Information
- Marin Water Construction Management team: 415-945-1560
Investing in your water system
This project will improve fire flow and seismic reliability of the system in support of the District's Fire Flow Improvement Program, a voter-approved initiative that helps boost water flows to hydrants for emergency response purposes.
Funding Sources
Capital Maintenance Fund | Fire Flow Improvement Program Fund | Total |
- | $2,000,000 | $2,000,000 |