Wolfback Ridge - Fire Flow Improvement Program

Project Wolfback Ridge - Fire Flow Improvement Program 
Program A2A Fire Flow Improvement Program 
Project Number F18002
Contact Matthew Steiner | MSteiner@marinwater.org 
Image
Map of pipe location across highway 101 near the Wolfback Ridge Pump Station and Beacon Hill Tank
Image
Overpass across highway

Project Description 

Installation of approximately 2,200 feet of 8-inch welded steel pipe to replace leak prone 1953 6-inch cast iron pipe that crosses beneath Highway 101. This project is to improve fireflow and seismic reliability of the system in this area. 

Benefits

The benefit of this project is to replace and relocate old leak prone, seismically deficient pipe from beneath Hwy 101 onto a freeway over pass, which will improve accessibility for maintenance and improve fire flow and seismic resiliency of the system and eliminate the impact to traffic on Hwy 101.  

Schedule and Status

Planning: Summer 2017 - Spring 2023

Design: Spring 2023 - Spring 2024

Construction: Spring 2024 - Fall 2024

Expenditure Schedule

Actuals Through
FY 22 (Rounded)
FY 23
Estimate 
FY 24
Estimate 
FY 25
Estimate 
Total
$28,000
$80,000
$150,000
$2,000,000
$2,258,000

Funding Sources 

Capital Maintenance Fund
Fire Flow Improvement Program Fund
Total
-
$2,258,000
$2,258,000