Project | Phoenix-Bon Tempe Connection Project |
Program | Pump Stations | A1A07 Transmission Pumps |
Project Number | D22010 |
Contact | Hagar Nagesh | hnegash@marinwater.org |
Notice: The Draft CEQA Initial Study/Mitigated Negative Declaration document for the Phoenix-Bon Tempe Connection Project is available for public review. Public comments related to this project document may be sent to eirish@marinwater.org through April 12, 2024. |
Project Description
This project includes system improvements at the Phoenix Transfer Pump Station, including a new raw water pump station and installation of approximately 7,700 feet of 12-inch pipe to allow for pumping of Phoenix Lake water into Bon Tempe Reservoir.
Benefits
Connecting these two Mount Tamalpais Watershed reservoirs will increase operational efficiency by allowing more frequent use of Phoenix Lake water without intensive system modifications. This will ultimately yield a potential increase of 260 acre-feet of water into Bon Tempe Reservoir each year, improving drought resiliency. The Phoenix-Bon Tempe Connection Project is part of Marin Water's Strategic Water Supply Roadmap, which includes a robust mix of short-term water supply strategies, as well as pre-design work to support medium- and longer-term strategies.
Schedule and Status
Planning: Spring 2023 - Fall 2023
Design: Spring 2023 - Summer 2024
Construction: Summer 2024 - Winter 2026
Funding Sources
Capital Maintenance Fund | Other Funding Sources | Total |
$5,200,000 | - | $5,200,000 |