This project will replace the two redwood Hind Tanks with a single, 300,000-gallon, pre-stressed concrete tank. Once complete, just two aging, leak-prone redwood storage tanks will remain in the District's system.
Schedule and Status
Planning: Summer 2007 - Summer 2023
Design: Summer 2023 - Winter 2025
Construction: Winter 2025 - Summer 2025
Contact Information
- Marin Water Construction Management team: 415-945-1560
Investing in your water system
This tank replacement project removes two seismically deficient, leak-prone redwood tanks from the Marin Water distribution system, replacing them with a pre-stressed tank that is seismically resilient and fire hardened, resulting in a more resilient water infrastructure system.
Funding Sources
Capital Maintenance Fund | Other Funding Sources | Total |
$1,500,000 | - | $1,500,000 |